SAFe Agilist (Leading SAFe) · Current exam · Updated 2026
Free SAFe Agilist Practice Exam (2026)
Full-length SAFe Agilist mock exams with the same number of questions and time as the real Leading SAFe exam. Lean-Agile mindset, ARTs, PI Planning, Lean Portfolio Management and leadership questions, answers explained, and your score by domain.
1. Choose a set
2. Choose a mode
45 questions · 1 hour 30 min · same as the real exam
You have an unfinished attempt on this set.
Questions 1–10Page 1 of 5
🏆
Question 1Product Development Flow
A health app ART wants to redesign appointment booking. The team jumps straight into building screens based on what managers think patients want. Which design thinking step should come FIRST?
Correct answer: C. Research patient needs using tools like personas and empathy maps
Design thinking starts in the problem space by understanding users and their needs before building solutions. Personas and empathy maps help teams see the problem from the customer's view. Writing stories from manager assumptions risks building the wrong thing.
Design thinking starts in the problem space by understanding users and their needs before building solutions. Personas and empathy maps help teams see the problem from the customer's view. Writing stories from manager assumptions risks building the wrong thing.
Question 2Mindset, Values & Principles
On the Solaris ART, teams report every feature as 'green' until the last week of the PI, when several suddenly turn red. Leaders are frustrated by the late surprises. Which SAFe core value is MOST clearly missing?
Correct answer: B. Transparency
Transparency means sharing facts, including bad news, early and openly so problems can be fixed while there is still time. Trust grows when people feel safe to show real status. Program execution is about delivering value, but the root problem here is hidden information.
Transparency means sharing facts, including bad news, early and openly so problems can be fixed while there is still time. Trust grows when people feel safe to show real status. Program execution is about delivering value, but the root problem here is hidden information.
Question 3Lean Portfolio Management
The LPM team at Arcadia Insurance wants a one-page view of the portfolio's current value propositions, customers, solutions, costs and revenue so it can explore alternative future states. Which tool BEST fits?
Correct answer: D. The portfolio canvas
The portfolio canvas, adapted from the Business Model Canvas, describes the current state of a portfolio, including value propositions, customers, solutions, costs and revenue. Leaders use it to explore possible future states. A Lean business case describes a single epic.
The portfolio canvas, adapted from the Business Model Canvas, describes the current state of a portfolio, including value propositions, customers, solutions, costs and revenue. Leaders use it to explore possible future states. A Lean business case describes a single epic.
Question 4Team & Technical Agility
StreamCo has several stream-aligned teams building video features. One component needs deep expertise in compression math that only a few specialists have. Which team type BEST fits the group that owns this component?
Correct answer: A. Complicated subsystem team
A complicated subsystem team owns a part of the system that requires deep specialist knowledge, which reduces cognitive load on stream-aligned teams. An enabling team helps other teams build new skills for a limited time rather than owning a component.
A complicated subsystem team owns a part of the system that requires deep specialist knowledge, which reduces cognitive load on stream-aligned teams. An enabling team helps other teams build new skills for a limited time rather than owning a component.
Question 5Adapt & Thrive
Halvern Insurance has a strong functional hierarchy that runs operations reliably, but new digital products take 18 months to reach customers. Executives want to keep operational stability while moving much faster. Which approach BEST reflects SAFe guidance?
Correct answer: B. Add a value network organized around value streams that works alongside the hierarchy
SAFe describes a dual operating system: the hierarchy keeps providing stability and efficiency, while a value network organized around value streams delivers speed and innovation. Replacing the hierarchy entirely throws away what it does well, and SAFe does not ask for that.
SAFe describes a dual operating system: the hierarchy keeps providing stability and efficiency, while a value network organized around value streams delivers speed and innovation. Replacing the hierarchy entirely throws away what it does well, and SAFe does not ask for that.
Question 6Product Development Flow
A Product Manager writes a backlog item: 'Customers can pay with digital wallets.' It will take several teams about six weeks, and it includes a benefit hypothesis. How should this item be classified?
Correct answer: A. A feature, owned by Product Management, sized to fit in a PI
A feature meets a stakeholder need, includes a benefit hypothesis and acceptance criteria, and is sized for an ART to deliver within a PI. Product Management owns features. Stories fit within one iteration, and epics are larger initiatives that usually span several PIs.
A feature meets a stakeholder need, includes a benefit hypothesis and acceptance criteria, and is sized for an ART to deliver within a PI. Product Management owns features. Stories fit within one iteration, and epics are larger initiatives that usually span several PIs.
Question 7Lead the Change
Executives at Fairmont Logistics funded a SAFe transformation, but they skip PI Planning and keep requesting status reports instead of attending system demos. What should these Lean-Agile leaders do differently?
Correct answer: D. Take part in key events like PI Planning and system demos
Leading by example means leaders model the behaviors they expect, such as joining PI Planning and system demos and engaging directly with teams. Asking for more reports keeps leaders away from real information and signals that the change is someone else's job.
Leading by example means leaders model the behaviors they expect, such as joining PI Planning and system demos and engaging directly with teams. Asking for more reports keeps leaders away from real information and signals that the change is someone else's job.
Question 8Mindset, Values & Principles
A team at Brightway Health spends three weeks of each month writing detailed design documents that stakeholders rarely read. Little working functionality is ever demonstrated. Which Agile Manifesto value does this MOST directly conflict with?
Correct answer: A. Working software over comprehensive documentation
The manifesto values working software over comprehensive documentation. Documents still have some value, but working functionality is the primary measure of progress, and this team invests heavily in documents while showing little working product.
The manifesto values working software over comprehensive documentation. Documents still have some value, but working functionality is the primary measure of progress, and this team invests heavily in documents while showing little working product.
Question 9Lean Portfolio Management
Executives at Norland Telecom define 'Expand into small business markets' and 'Become cloud-first' as differentiating business objectives for the next few years. How do these strategic themes MOSTLY influence the portfolio?
Correct answer: C. They guide the portfolio vision, budgets and epic priorities
Strategic themes are differentiating business objectives that connect the portfolio to enterprise strategy. They influence the portfolio vision, Lean budget allocations and the prioritization of epics. They are not detailed scope commitments or team iteration goals.
Strategic themes are differentiating business objectives that connect the portfolio to enterprise strategy. They influence the portfolio vision, Lean budget allocations and the prioritization of epics. They are not detailed scope commitments or team iteration goals.
Question 10Product Development Flow
The Delta ART plans customer features for next PI that depend on a new event-streaming platform that does not exist yet. What should the ART add to its backlog to prepare?
Correct answer: A. An architectural enabler that builds the runway ahead of the features
Enablers support upcoming business functionality, and architectural enablers build the architectural runway that future features need. Without runway, teams face delays and rework when the features arrive. Treating it as optional cleanup puts the planned features at risk.
Enablers support upcoming business functionality, and architectural enablers build the architectural runway that future features need. Without runway, teams face delays and rework when the features arrive. Treating it as optional cleanup puts the planned features at risk.
Question 11Mindset, Values & Principles
Two teams at Corvel Logistics argue over whether to delay a release by one month to add an extra reporting feature. Using SAFe Principle #1, what should guide the decision MOST?
Correct answer: D. The impact on total lifecycle profit, including the cost of delay
Taking an economic view means making decisions based on economic impact over the solution's lifecycle, including the cost of delaying value. Following the original plan ignores what has been learned since it was written.
Taking an economic view means making decisions based on economic impact over the solution's lifecycle, including the cost of delaying value. Following the original plan ignores what has been learned since it was written.
Question 12Lean Portfolio Management
At Medivia Clinics, the steps from a patient booking an appointment to receiving treatment and paying the bill form one flow. The people who build the scheduling and billing systems form another. Which statement is correct?
Correct answer: B. The first is operational; the second is a development value stream
Operational value streams are the steps that deliver goods or services to the customer, such as a patient's care journey. Development value streams are the people and steps that build the solutions operational value streams use, such as scheduling and billing systems.
Operational value streams are the steps that deliver goods or services to the customer, such as a patient's care journey. Development value streams are the people and steps that build the solutions operational value streams use, such as scheduling and billing systems.
Question 13Product Development Flow
It is the morning of day 1 of PI Planning at Crestline Bank. Which presentation is MOST important for giving teams the content they will plan?
Correct answer: C. Product Management presents the vision and top ART backlog features
Day 1 of PI Planning includes business context, the product vision with the highest-priority features from the ART backlog, and the architecture vision. These inputs give teams the content they need to plan. A complete detailed design is not expected up front.
Day 1 of PI Planning includes business context, the product vision with the highest-priority features from the ART backlog, and the architecture vision. These inputs give teams the content they need to plan. A complete detailed design is not expected up front.
Question 14Team & Technical Agility
A team at Lumen Retail keeps getting interrupted by managers adding work mid-iteration, and its retrospectives have turned into complaint sessions with no actions. Which role is PRIMARILY responsible for helping the team address this?
Correct answer: B. Scrum Master/Team Coach
The Scrum Master/Team Coach is a servant leader who coaches the team, facilitates events such as retrospectives and helps remove impediments like mid-iteration interruptions. The RTE plays a similar role for the whole ART, not for one team's daily practices.
The Scrum Master/Team Coach is a servant leader who coaches the team, facilitates events such as retrospectives and helps remove impediments like mid-iteration interruptions. The RTE plays a similar role for the whole ART, not for one team's daily practices.
Question 15Adapt & Thrive
A retail CEO tells her leadership team, 'We need business agility.' Which description BEST matches what SAFe means by that term?
Correct answer: D. Responding quickly to market changes with innovative, digitally enabled solutions
Business agility is the ability to compete and thrive by responding quickly to market changes and emerging opportunities with innovative business solutions. It is an enterprise-wide capability, not just Scrum adoption in IT or higher feature counts.
Business agility is the ability to compete and thrive by responding quickly to market changes and emerging opportunities with innovative business solutions. It is an enterprise-wide capability, not just Scrum adoption in IT or higher feature counts.
Question 16Mindset, Values & Principles
Nexis Robotics must choose between two battery technologies for a new product, but test data will not be available for several months. A manager wants to pick one now so detailed design can begin. Which approach BEST applies SAFe Principle #3?
Correct answer: B. Keep both options open and narrow them as test data reduces uncertainty
Assume variability and preserve options promotes set-based design: keep multiple design options open and eliminate weaker ones as knowledge emerges. Choosing early forces a point solution that may cause costly rework, and stopping all work wastes learning time.
Assume variability and preserve options promotes set-based design: keep multiple design options open and eliminate weaker ones as knowledge emerges. Choosing early forces a point solution that may cause costly rework, and stopping all work wastes learning time.
Question 17Lean Portfolio Management
Kestrel Financial funds work through annual projects, each requiring a detailed business case and cost tracking. Teams are formed and disbanded for every project. What change does SAFe Lean Portfolio Management recommend?
Correct answer: C. Fund long-lived value streams instead of individual projects
Lean budgets fund value streams, which allows stable, long-lived ARTs and removes much of the overhead of project-based funding and cost accounting. Funding by story points or fully specified features would recreate the delays of project funding.
Lean budgets fund value streams, which allows stable, long-lived ARTs and removes much of the overhead of project-based funding and cost accounting. Funding by story points or fully specified features would recreate the delays of project funding.
Question 18Product Development Flow
During PI Planning, the Comet team has drafted its PI objectives and wants to know how important each one is to the business. Who assigns business value to the objectives, and on what scale?
Correct answer: A. The Business Owners, on a scale of 1 to 10
Business Owners assign business value to each team PI objective, typically on a scale of 1 to 10, while talking with the team on day 2. This shows teams what matters most. The scores are later compared with the value actually achieved.
Business Owners assign business value to each team PI objective, typically on a scale of 1 to 10, while talking with the team on day 2. This shows teams what matters most. The scores are later compared with the value actually achieved.
Question 19Lead the Change
Corvane Manufacturing is profitable with no immediate crisis, but its CEO sees digital competitors emerging. Which approach BEST helps the company reach the tipping point for a SAFe transformation?
Correct answer: D. Leaders proactively create urgency with a compelling vision
SAFe notes the tipping point can come from a burning platform or from proactive leadership that creates urgency with a compelling vision. The CEO does not need to wait for a crisis, and launching ARTs without explaining why weakens commitment.
SAFe notes the tipping point can come from a burning platform or from proactive leadership that creates urgency with a compelling vision. The CEO does not need to wait for a crisis, and launching ARTs without explaining why weakens commitment.
Question 20Mindset, Values & Principles
A government contractor uses phase gates where a project passes once its requirements and design documents are signed off. Leadership wants a better way to know whether real progress is being made. What does SAFe recommend?
Correct answer: A. Evaluate working, integrated system increments at regular milestones
Principle #5 says milestones should be based on objective evaluation of working systems. Integrated increments, demonstrated regularly, show real progress and reduce risk. Task completion and signed documents can look healthy while the real system does not work.
Principle #5 says milestones should be based on objective evaluation of working systems. Integrated increments, demonstrated regularly, show real progress and reduce risk. Task completion and signed documents can look healthy while the real system does not work.
Question 21Lean Portfolio Management
A value stream at Orbit Media wants to start an initiative estimated at $4 million. The portfolio's guardrail says any epic over $2 million needs LPM approval. What must happen?
Correct answer: C. It goes through the portfolio Kanban and needs LPM approval
One Lean budget guardrail is approving significant initiatives: epics above the portfolio threshold need a Lean business case and LPM approval. Splitting work just to dodge the threshold defeats the purpose of the guardrail.
One Lean budget guardrail is approving significant initiatives: epics above the portfolio threshold need a Lean business case and LPM approval. Splitting work just to dodge the threshold defeats the purpose of the guardrail.
Question 22Product Development Flow
The Zephyr team thinks it can probably deliver a reporting improvement this PI, but the work depends on an uncertain vendor API. The team does not want to make a firm commitment. How should it handle this objective?
Correct answer: D. Plan it as an uncommitted objective with business value assigned
Uncommitted objectives are planned and given business value, but they are not part of the commitment because they carry low certainty. They give flexibility while keeping the work visible. Using the IP iteration as overflow for planned work is an anti-pattern.
Uncommitted objectives are planned and given business value, but they are not part of the commitment because they carry low certainty. They give flexibility while keeping the work visible. Using the IP iteration as overflow for planned work is an anti-pattern.
Question 23Team & Technical Agility
During a PI, three teams on the Atlas ART are blocked by a shared impediment with an external vendor. No single team can resolve it. Who is BEST placed to facilitate escalation and resolution at the ART level?
Correct answer: D. The Release Train Engineer
The Release Train Engineer is the servant leader and coach for the ART who facilitates ART events, manages risks and escalates impediments that span teams. A Product Owner focuses on one team's backlog, and the Epic Owner works on portfolio epics.
The Release Train Engineer is the servant leader and coach for the ART who facilitates ART events, manages risks and escalates impediments that span teams. A Product Owner focuses on one team's backlog, and the Epic Owner works on portfolio epics.
Question 24Product Development Flow
At the end of PI Planning, the Halcyon ART holds a confidence vote. Several teams vote with one or two fingers, mainly because of unresolved dependencies. What should happen NEXT?
Correct answer: B. Address the concerns and adjust plans until confidence is acceptable
Low confidence votes signal real problems. The concerns should be raised and addressed, sometimes with rework of the plans, until the ART can commit with reasonable confidence. Waiting until Inspect and Adapt or pressuring voters only hides the risk.
Low confidence votes signal real problems. The concerns should be raised and addressed, sometimes with rework of the plans, until the ART can commit with reasonable confidence. Waiting until Inspect and Adapt or pressuring voters only hides the risk.
Question 25Mindset, Values & Principles
The CTO of Pinehurst Software plans to boost productivity by paying individual bonuses based on how many stories each developer completes. Based on SAFe Principle #8, what is the MOST likely concern?
Correct answer: C. Individual rewards can undermine collaboration and intrinsic motivation
Unlocking the intrinsic motivation of knowledge workers means avoiding individual incentives tied to output, which create competition and gaming. Knowledge workers respond better to autonomy, mastery and purpose. Switching to hours or lines of code just changes which number gets gamed.
Unlocking the intrinsic motivation of knowledge workers means avoiding individual incentives tied to output, which create competition and gaming. Knowledge workers respond better to autonomy, mastery and purpose. Switching to hours or lines of code just changes which number gets gamed.
Question 26Lean Portfolio Management
An epic at Silverpine Retail has been pulled from Reviewing into the Analyzing state of the portfolio Kanban. Which activity happens MAINLY in this state?
Correct answer: D. The Epic Owner builds a Lean business case and defines an MVP
In Analyzing, the Epic Owner works with others to explore solution alternatives, define the MVP and build the Lean business case for a go or no-go decision. New ideas enter in the Funnel, and implementation starts only after approval.
In Analyzing, the Epic Owner works with others to explore solution alternatives, define the MVP and build the Lean business case for a go or no-go decision. New ideas enter in the Funnel, and implementation starts only after approval.
Question 27Adapt & Thrive
A 90-person software company wants to start with SAFe. It has one product and will form a single Agile Release Train. Which SAFe configuration is the MOST appropriate starting point?
Correct answer: C. Essential SAFe
Essential SAFe is the basic building block, containing the Agile teams and the ART, and it is the minimum needed to be doing SAFe. Large Solution SAFe adds Solution Trains for very big systems that need multiple ARTs and suppliers, which this company does not have.
Essential SAFe is the basic building block, containing the Agile teams and the ART, and it is the minimum needed to be doing SAFe. Large Solution SAFe adds Solution Trains for very big systems that need multiple ARTs and suppliers, which this company does not have.
Question 28Lead the Change
Brookfield Group is ready to start its SAFe implementation. Who should form the guiding coalition that leads the change?
Correct answer: B. SPCs, executives and leaders, and a Lean-Agile Center of Excellence
The guiding coalition typically includes trained change agents such as SPCs, executives and leaders who sponsor the change, and a LACE that drives it day to day. A group of IT team leads lacks the authority and reach needed for an enterprise change.
The guiding coalition typically includes trained change agents such as SPCs, executives and leaders who sponsor the change, and a LACE that drives it day to day. A group of IT team leads lacks the authority and reach needed for an enterprise change.
Question 29Product Development Flow
Halfway through day 2 of PI Planning, the RTE wants a single view of when each feature will be delivered, the dependencies between teams and key milestones. Which artifact provides this?
Correct answer: C. The ART planning board
The ART planning board, formerly called the program board, shows feature delivery dates, dependencies between teams and with other ARTs, and relevant milestones. The portfolio canvas and Lean business case are portfolio-level artifacts.
The ART planning board, formerly called the program board, shows feature delivery dates, dependencies between teams and with other ARTs, and relevant milestones. The portfolio canvas and Lean business case are portfolio-level artifacts.
Question 30Mindset, Values & Principles
Leaders at Quintra Bank are deciding which decisions to keep centralized. Which decision is the BEST candidate to remain centralized?
Correct answer: A. Selecting a company-wide cloud provider for the next five years
Principle #9 says to centralize decisions that are infrequent, long-lasting and have significant economies of scale, such as a strategic platform choice. Frequent, time-critical decisions that need local knowledge, like task breakdown or defect order, should be decentralized.
Principle #9 says to centralize decisions that are infrequent, long-lasting and have significant economies of scale, such as a strategic platform choice. Frequent, time-critical decisions that need local knowledge, like task breakdown or defect order, should be decentralized.
Question 31Lean Portfolio Management
Polaris Travel approved an epic and built its MVP. The leading indicators show customers are not using the new capability as hoped. What is the MOST appropriate next step?
Correct answer: B. Pivot or stop, based on the evidence
The MVP tests the epic's hypothesis. If leading indicators do not support it, the portfolio should pivot to a new hypothesis or stop investing. Continuing as planned ignores the evidence, which is exactly the waste the MVP approach is meant to prevent.
The MVP tests the epic's hypothesis. If leading indicators do not support it, the portfolio should pivot to a new hypothesis or stop investing. Continuing as planned ignores the evidence, which is exactly the waste the MVP approach is meant to prevent.
Question 32Team & Technical Agility
Defects on the Keystone team are usually found by a separate QA group weeks after the code is written. The team wants to find problems earlier and design better code. Which practice BEST supports built-in quality?
Correct answer: A. Write automated tests before or alongside the code
Test-first practices such as TDD and BDD shift learning left, so defects are caught minutes after they are created and tests guide a cleaner design. A hardening phase delays feedback and lets quality problems pile up instead of preventing them.
Test-first practices such as TDD and BDD shift learning left, so defects are caught minutes after they are created and tests guide a cleaner design. A hardening phase delays feedback and lets quality problems pile up instead of preventing them.
Question 33Product Development Flow
On the Vega ART, each team demos its stories separately in its own environment, and integration happens only at the end of the PI. Which change BEST aligns with SAFe?
Correct answer: C. Hold a system demo of the integrated increment every iteration
The system demo shows the integrated work of all teams on the ART at the end of each iteration, giving objective evidence of progress and early feedback. Leaving integration to the end of the PI hides risk until it is expensive to fix.
The system demo shows the integrated work of all teams on the ART at the end of each iteration, giving objective evidence of progress and early feedback. Leaving integration to the end of the PI hides risk until it is expensive to fix.
Question 34Mindset, Values & Principles
Product Management at Velora Media scores four features as user-business value, time criticality, risk reduction/opportunity enablement, and job size. W: 8, 5, 3, size 8. X: 5, 8, 2, size 3. Y: 13, 8, 5, size 13. Z: 3, 3, 8, size 5. Using WSJF, which feature should be done FIRST?
Correct answer: D. Feature X
WSJF is Cost of Delay divided by job size, and Cost of Delay is the sum of the three value components. W = 16 / 8 = 2.0, X = 15 / 3 = 5.0, Y = 26 / 13 = 2.0 and Z = 14 / 5 = 2.8, so X goes first. Y has the highest Cost of Delay, but its large size lowers its WSJF.
WSJF is Cost of Delay divided by job size, and Cost of Delay is the sum of the three value components. W = 16 / 8 = 2.0, X = 15 / 3 = 5.0, Y = 26 / 13 = 2.0 and Z = 14 / 5 = 2.8, so X goes first. Y has the highest Cost of Delay, but its large size lowers its WSJF.
Question 35Lean Portfolio Management
LPM has just approved an epic at Granite Energy. Someone now needs to work with Product Management on the affected ARTs to split it into features, help the ARTs during implementation and track progress against the hypothesis. Which role fits BEST?
Correct answer: D. Epic Owner
After approval, the Epic Owner stays with the epic, working with Product Management to define features for the ART backlogs and supporting the ARTs through implementation. The RTE facilitates the ART's events and flow rather than owning a portfolio epic.
After approval, the Epic Owner stays with the epic, working with Product Management to define features for the ART backlogs and supporting the ARTs through implementation. The RTE facilitates the ART's events and flow rather than owning a portfolio epic.
Question 36Product Development Flow
In a problem-solving workshop, the Titan ART agrees on its problem statement and uses a fishbone diagram with the 5 Whys to find several possible causes. What should the group do NEXT?
Correct answer: A. Identify the biggest root cause using Pareto analysis and voting
After root cause analysis, the group identifies the biggest root cause, often with Pareto analysis and voting, and restates the problem around it before brainstorming solutions. Jumping to solutions for every cause spreads effort thin and skips the focus step.
After root cause analysis, the group identifies the biggest root cause, often with Pareto analysis and voting, and restates the problem around it before brainstorming solutions. Jumping to solutions for every cause spreads effort thin and skips the focus step.
Question 37Adapt & Thrive
Aerovant builds flight control systems. Delivery needs five ARTs plus two external suppliers, all contributing to one complex solution with strict compliance needs. Strategy and funding are handled elsewhere. Which configuration adds the roles and events they need MOST?
Correct answer: B. Large Solution SAFe with a Solution Train
Large Solution SAFe adds the Solution Train, Solution Management and Solution Train Engineer to coordinate multiple ARTs and suppliers building one large system. Portfolio SAFe addresses strategy and funding, which the question says is handled elsewhere.
Large Solution SAFe adds the Solution Train, Solution Management and Solution Train Engineer to coordinate multiple ARTs and suppliers building one large system. Portfolio SAFe addresses strategy and funding, which the question says is handled elsewhere.
Question 38Mindset, Values & Principles
In the SAFe House of Lean, what sits at the top as the goal that the pillars and the foundation support?
Correct answer: D. Value
The goal of the SAFe House of Lean is value: the best quality and value to people and society in the shortest sustainable lead time. Flow and innovation are pillars that support that goal, and leadership is the foundation.
The goal of the SAFe House of Lean is value: the best quality and value to people and society in the shortest sustainable lead time. Flow and innovation are pillars that support that goal, and leadership is the foundation.
Question 39Lean Portfolio Management
The LPM team at Helix Pharma suspects that ARTs spend almost all their capacity on new features while technical debt grows. Which flow metric would MOST directly show this?
Correct answer: C. Flow distribution
Flow distribution shows the proportion of different work types, such as features, enablers, defects and debt, in a system, so it reveals whether capacity is balanced. Flow velocity counts how many items are completed, not what kind they are.
Flow distribution shows the proportion of different work types, such as features, enablers, defects and debt, in a system, so it reveals whether capacity is balanced. Flow velocity counts how many items are completed, not what kind they are.
Question 40Product Development Flow
The Nova ART regularly leaves feature work unfinished and plans to complete it during the IP iteration. What is the MAIN problem with this practice?
Correct answer: B. It removes time meant for innovation, learning, planning and buffer
The IP iteration provides time for innovation, continuing education, PI Planning, Inspect and Adapt, and a buffer against estimation errors. Routinely using it to finish planned features removes that buffer and hides poor predictability.
The IP iteration provides time for innovation, continuing education, PI Planning, Inspect and Adapt, and a buffer against estimation errors. Routinely using it to finish planned features removes that buffer and hides poor predictability.
Question 41Lead the Change
A portfolio leader at Westbridge Bank wants to paste confidential customer contract details into a public AI chatbot to summarize risks before a strategy meeting. What is the MOST responsible action?
Correct answer: C. Use an approved tool that protects the data, and verify the output
Leaders who use AI responsibly protect sensitive data by following approved tools and policies, and they check AI output before relying on it. Sharing confidential data with an unapproved public tool creates real risk, while banning AI entirely gives up its benefits.
Leaders who use AI responsibly protect sensitive data by following approved tools and policies, and they check AI output before relying on it. Sharing confidential data with an unapproved public tool creates real risk, while banning AI entirely gives up its benefits.
Question 42Team & Technical Agility
On the Meridian ART, Product Management is researching market needs, testing hypotheses with customers and defining features for the ART backlog. Which aspect of the Continuous Delivery Pipeline is this?
Correct answer: A. Continuous Exploration
Continuous Exploration is where the ART learns customer needs, forms hypotheses, explores solutions and creates and refines features. Continuous Integration then builds, integrates and tests those features.
Continuous Exploration is where the ART learns customer needs, forms hypotheses, explores solutions and creates and refines features. Continuous Integration then builds, integrates and tests those features.
Question 43Mindset, Values & Principles
The Orion ART starts using AI assistants to draft acceptance tests, summarize customer feedback and flag risky code changes. A manager asks how this fits with SAFe. Which view is MOST consistent with SAFe?
Correct answer: B. AI is an enabler that can speed learning and flow while people stay accountable
SAFe treats AI as an enabler that augments people, helping teams learn faster and improve flow. People remain accountable for decisions and quality, so AI output still needs review. AI does not remove the need for customer collaboration or Lean-Agile practices.
SAFe treats AI as an enabler that augments people, helping teams learn faster and improve flow. People remain accountable for decisions and quality, so AI output still needs review. AI does not remove the need for customer collaboration or Lean-Agile practices.
Question 44Lean Portfolio Management
Dalton Foods writes a strategic theme as the objective 'Delight online shoppers,' with measures such as 'Raise repeat purchase rate from 20% to 30%.' In OKR terms, what are these measures called?
Correct answer: A. Key results
In Objectives and Key Results, the objective is a qualitative goal and the key results are measurable outcomes that show progress toward it. SAFe often uses OKRs to express strategic themes. Acceptance criteria apply to features and stories, not strategy.
In Objectives and Key Results, the objective is a qualitative goal and the key results are measurable outcomes that show progress toward it. SAFe often uses OKRs to express strategic themes. Acceptance criteria apply to features and stories, not strategy.
Question 45Product Development Flow
Fintrex deploys code to production every day, but marketing wants new features released to customers only when a campaign starts. What technique BEST supports this?
Correct answer: C. Use feature toggles to separate deployment from release
SAFe separates deployment from release. Feature toggles let code sit in production hidden from users until the business decides to switch it on, so daily deployment continues. Long-lived branches delay integration and increase merge risk.
SAFe separates deployment from release. Feature toggles let code sit in production hidden from users until the business decides to switch it on, so daily deployment continues. Long-lived branches delay integration and increase merge risk.
The real SAFe Agilist exam at a glance
45questions
1h 30mtime limit
MCQmultiple choice
85%+aim for here
Score 85% or more on two different sets before you book the real exam. Need a plan for your weak topics? See how we help you pass, or get a full refund.
More free Project Management & Agile practice tests
PMP Practice Test180 questions · New 2026 examPMI-ACP Practice Test120 questions · AgilePgMP Practice Test170 questions · Program ManagementPRINCE2 Foundation Practice Test60 questions · PRINCE2 7Scrum Master (CSM) Practice Test50 questions · Scrum Guide 2020
See all 36 free practice tests →
Original practice questions written by CertOcean in the style of the SAFe Agilist exam. They are not real exam questions. SAFe Agilist and Scaled Agile are trademarks of their owners. Real exam format: 45 questions · 90 minutes · passing score 80%.